Prince 2 - Foundation

94%

Question 321

What are acceptance criteria?
The methods used to prove whether the project's products have been completed
Measurable improvements resulting from a project outcome
Measurable definitions of the attributes for a set of products to be acceptable to key stakeholders
Project controls that are established during the 'initiating a project' process




Answer is Measurable definitions of the attributes for a set of products to be acceptable to key stakeholders

Reference:
https://hennyportman.wordpress.com/2010/02/19/prince2-in-practice-acceptance-criteria-building-block-update/

Question 322

Which is an advantage of applying the continued business justification principle?
Legislative projects do not require a business justification before initiation
Duplication of project objectives is less likely across an organizationג€™s portfolio
All projects have a business justification documented in a formal business case
Regular revalidation ensure that all funds allocated to the project will be used




Answer is All projects have a business justification documented in a formal business case

Reference:
https://www.simplilearn.com/prince2-structure-and-benefits-in-project-management-article

Question 323

Which TWO create desired outcomes?

1. Business changes
2. Project outputs
3. Benefits
4. Strategic objectives
1 and 2
2 and 3
3 and 4
1 and 4




Answer is 2 and 3

Expected benefits These result from the desired outcomes to be achieved through the use of the project outputs. The benefits are expressed in measurable terms against the situation as it exists prior to the project.

Reference:
Prince2 guide - A.2.2

Question 324

What should the project manager do to support the learn from experience principle?
Incorporate lessons identified into the regular checkpoint report
Seek supplier experiences when considering the project approach
Summarize project lessons in a lessons log during project closure
Produce the executive's role description and responsibilities




Answer is Summarize project lessons in a lessons log during project closure


Question 325

Which document would be updated at the end of a stage to include information needs for a new stakeholder?
Benefits management approach
Quality management approach
Communication management approach
End stage report




Answer is Communication management approach


Question 326

Which is a minimum requirement for applying the organization theme?
To provide unified direction to the project through a democratic project board
To delegate responsibility for managing product delivery to team managers
To allocate a separate group to carry out project support tasks
To document the rules for delegating change authority responsibilities, if required




Answer is To document the rules for delegating change authority responsibilities, if required


Question 327

Which statement about tailoring roles is CORRECT?
The PRINCE2 roles should not be tailored
The accountability of each role should be maintained
The defined roles and responsibilities principle can be ignored
The project management team should proactively tailor their own roles




Answer is The accountability of each role should be maintained


Question 328

Which project management team role can be combined with business assurance?
Project support
Senior supplier
Executive
Project manager




Answer is Executive

An important responsibility of the PRINCE2 project board is project assurance. This is part of the PRINCE2 project management team, and consists of three roles, business assurance, user assurance, and supplier assurance.

Executive = Business Assurance, Senior Supplier = Supplier Assurance, Senior User = User Assurange

Reference:
https://www.prince2primer.com/design-and-appoint-the-project-management-team/

Question 329

Identify the missing words in the following sentence;

A purpose of the [?] process is to enable an organization to understand the work required for project delivery, before committing to a significant spend.
controlling a stage
directing a project
initiating a project
managing product delivery




Answer is initiating a project

Reference:
https://www.siliconbeachtraining.co.uk/blog/prince2-initiating-project-process-ip

Question 330

Which role can act as the change authority?
Project assurance
Team manager
Project support
Team member




Answer is Project assurance

"The project manager and/or the people with delegated project assurance responsibilities may act as the change authority. Refer to Chapter 11 for more information on change."

Reference:
Section "7.2.1.6 Change Authority" from PRINCE2 manual: