Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project
Which is a minimum requirement for applying the organization theme?
Each member of the project management team must have a written role description
The roles of the project management team must be combined, wherever possible
The project manager must be appointed from the supplier organization
The frequency of communication to the project's stakeholders must be documented
Answer is The frequency of communication to the project's stakeholders must be documented
Minimum requirements
You must define your project's organization structure and roles (by ensuring all responsibilities in PRINCE2’s role descriptions are fulfilled). You must define your project's approach to communicating and engaging with stakeholders and you must produce and maintain the project initiation documentation (PID), and a communication management approach.
Reference:
https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes
Question 180
Which statement about time-driven controls is CORRECT?
Time-driven controls are used for monitoring the progress of work packages and management stages
Time-driven controls take place when specific events happen
Time-driven controls are produced at the end of a stage
An exception report is a time-driven control
Answer is Time-driven controls are used for monitoring the progress of work packages and management stages