Prince 2 - Foundation

68%

Question 231

Which describes an off-specification?
An interdependency between products that was previously unidentified
The addition of an improvement to a product description
A prototype demonstrating a possible design solution
The production of more than the defined quantity of a specialist product




Answer is An interdependency between products that was previously unidentified

Reference:
https://www.prince2primer.com/prince2-change-control/

Question 232

Which process monitors work that has been assigned to a team manager?
Controlling a stage
Directing a project
Managing a stage boundary
Managing product delivery




Answer is Controlling a stage

The purpose of the Controlling a Stage process (CS) is for the Project Manager to assign the work to be done, monitor this work, deal with issues, report Progress to the Project Board and take corrective action to ensure that the stage remains within tolerance.

Question 233

Which is a minimum requirement for applying the quality theme?
Appraisal methods of quality control must be carried out on products
A record must be kept of all the quality management activities that are planned
The quality review technique must be used when reviewing products
The quality management approach must align with corporate standards




Answer is A record must be kept of all the quality management activities that are planned


Question 234

Which approach must be followed as a minimum requirement for applying the plans theme?
Activity-based planning
Product-based planning
Agile
Risk management




Answer is Product-based planning


Question 235

Identify the missing words in the following sentence;
The project manager [ ? ] for day-to-day management of the project.
and the project board are responsible
and the team manager(s) are accountable
has responsibility
decides who is responsible




Answer is has responsibility

Reference:
http://prince2.wiki/Directing_a_Project

Question 236

What may be funded from a risk budget?
Corrections required due to off-specifications
Impact analysis of requests for change
Implementation of a fallback plan
Preparation of the risk management approach




Answer is Implementation of a fallback plan

Reference:
http://prince2.wiki/Risk#Risk_Budget

Question 237

Which is a minimum requirement for applying the organization theme?
To document the project management team structure
To define the experience required for each project role
To include external stakeholders on the project board
To train project team members in the use of PRINCE2




Answer is To document the project management team structure

Reference:
http://prince2.wiki/Themes#Organization_Theme

Question 238

Who represents the three project interests on a project?
Project manager
Project support
External project stakeholders
Project board




Answer is Project board

Reference:
http://prince2.wiki/Organization#Three_Project_Interests

Question 239

Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?
Defined roles and responsibilities
Learn from experience
Manage by exception
Focus on products




Answer is Learn from experience

Reference:
https://www.prince2primer.com/academy/uncategorized/

Question 240

What must a PRINCE2 project demonstrate?
Application of PRINCE2 principles
Application of proper leadership skills
Application of the activities in each process
Application of tools appropriate for the industry




Answer is Application of PRINCE2 principles


< Previous PageNext Page >