Which process monitors work that has been assigned to a team manager?
Controlling a stage
Directing a project
Managing a stage boundary
Managing product delivery
Answer is Controlling a stage
The purpose of the Controlling a Stage process (CS) is for the Project Manager to assign the work to be done, monitor this work, deal with issues, report Progress to the Project Board and take corrective action to ensure that the stage remains within tolerance.
Question 233
Which is a minimum requirement for applying the quality theme?
Appraisal methods of quality control must be carried out on products
A record must be kept of all the quality management activities that are planned
The quality review technique must be used when reviewing products
The quality management approach must align with corporate standards
Answer is A record must be kept of all the quality management activities that are planned
Question 234
Which approach must be followed as a minimum requirement for applying the plans theme?
Activity-based planning
Product-based planning
Agile
Risk management
Answer is Product-based planning
Question 235
Identify the missing words in the following sentence;
The project manager [ ? ] for day-to-day management of the project.