Prince 2 - Foundation

97%

Question 331

Identify the missing words in the following sentence;

A purpose of the managing a stage boundary process is to produce [?], if the project board requests that the current stage is re-planned following a tolerance deviation.
an exception report
an exception plan
a stage plan for the next stage
an updated stage plan




Answer is an exception plan


Question 332

Which role is responsible for ensuring that the project management team works well with all the functional units involved in the project?
Project board
Project manager
Team manager
Project assurance



Question 333

When might the controlling a stage process be used?
During the closing a project process
During the directing a project process
During the initiating a project process
During the starting a project process




Answer is During the closing a project process


Question 334

Which role ensures that the project outputs comply with the relevant standards?
Senior supplier
Executive
Project support
Senior user



Question 335

Which process aims to establish foundations in order to achieve a successful project?
Starting up a project
Initiating a project
Controlling a stage
Directing a project




Answer is Initiating a project

Reference:
https://www.prince2primer.com/prince2-exam-key-learning-points/

Question 336

Which product defines what the project must deliver in order to gain acceptance?
Quality management approach
Project product description
Stage plan
Business case




Answer is Project product description

Reference:
https://www.prince2.no/fagstoff-maler/project-product-description/

Question 337

From which perspective does the managing product delivery process view the project?
Corporate, programme management or the customer
Project board
Project manager
Team manager


Question 338

Which statement is CORRECT about representatives of the user stakeholder interest?
They have to ensure that the project justifies the business investment
They have to ensure that project expenditure provides good value for money
They have the understand the standards that need to be applied
They have to operate the project's outputs during their operational life




Answer is They have to operate the project's outputs during their operational life

User according to the Organization theme:
The user viewpoint represents those individuals or groups for whom some or all of the following will apply:
- they will use the outputs of the project to realize the benefits
- they will operate, maintain or support the project's outputs
- the outputs of the project will impact them.

Reference:
Prince 2 guide - 7.1

Question 339

Which is an objective of the controlling a stage process?
To review the business justification for the project
To replan the current stage when directed
To develop products to defined quality criteria
To produce a team plan for the work package




Answer is To produce a team plan for the work package

Reference:
https://www.greycampus.com/opencampus/prince-2-practitioner/activities-in-controlling-stage-process-in-prince2

Question 340

How should a risky and complex project be planned in order to meet the minimum requirements for applying the plans theme?
A specific plan must be produced for managing agreed risk responses
The project manager must consider having more management stages
The defined tolerances must be aligned to the project board's risk attitude
A diagram showing the product interdependencies must be produced




Answer is The project manager must consider having more management stages

Have at least two management stages: an initiation stage and at least one further management stage. The more complex and risky a project, the more management stages that will be required (PRINCE2's manage by stages principle)

Reference:
Prince2 manual, 9.2 (requirements for the plans theme)