Prince 2 - Foundation

22%

Question 71

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
Manage by stages
Manage by exception
Continued business justification
Learn from experience




Answer is Manage by exception


Question 72

Which role is responsible for creating Checkpoint Reports?
Senior Supplier
Team Manager
Change Authority
Project Support




Answer is Team Manager


Question 73

Identify the missing words in the following sentence:

A Project Manager agrees the [ ? ] with a Team Manager.
project cost tolerance
stage cost tolerance
Work Package cost tolerance
product cost tolerance




Answer is Work Package cost tolerance


Question 74

Which is a true statement about time-driven controls?
Time-driven controls are used for monitoring the progress of Work Packages and management stages
Time-driven controls take place when specific events happen
Time-driven controls are produced at the end of a stage
An Exception Report is a time-driven control




Answer is Time-driven controls are used for monitoring the progress of Work Packages and management stages


Question 75

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
Only 1 is true
Only 2 is true
Both 1 and 2 are true
Neither 1 or 2 are true




Answer is Both 1 and 2 are true


Question 76

What theme provides all management levels within the project management team with mechanisms for monitoring and control?
Progress
Change
Organization
Quality




Answer is Progress


Question 77

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
Corporate group
Project Board
Project Assurance
Executive




Answer is Corporate group


Question 78

Which is a FALSE statement about technical stages?
Can overlap with other technical stages
Typified by the use a particular set of specialist skills
Include the Managing a Stage Boundary process activities
Can span more than one management stage




Answer is Include the Managing a Stage Boundary process activities


Question 79

How should the Team Manager report that tolerances are forecast to be exceeded?
Create an Exception Report
Create a Highlight Report
Raise an issue
Grant a concession




Answer is Raise an issue


Question 80

Which statement about stages is true?
Management stages should be of the same duration
The use of technical stages is mandatory
The use of management stages is mandatory
Management stages are driven by specialist teams




Answer is The use of management stages is mandatory

In PRINCE2, a project must have at least two management stages:
● an initiation stage
● at least one further management stage. The more complex and risky a project is, the more management stages will be required.

< Previous PageNext Page >

Quick access to all questions in this exam