Prince 2 - Foundation

57%

Question 191

Within which integrated element does PRINCE2 set minimum requirements?
Themes
Processes
Principles
Project environment




Answer is Themes


Question 192

Which is a purpose of the 'controlling a stage' process?
To produce a team plan for the work to be assigned to a team manager
To select and implement actions that will resolve deviations from a plan within tolerance
To obtain approvals for products delivered in a work package
To update a project plan to incorporate the actuals from a stage plan




Answer is To select and implement actions that will resolve deviations from a plan within tolerance

Reference:
http://prince2.wiki/Controlling_a_Stage#Purpose

Question 193

Which is a purpose of a project brief?
To act as a base document which enables the project board to assess progress
To provide a sound basis for project initiation
To define how the achievement of the project's benefits can be measured
To provide a description of the means and frequency of communication




Answer is To provide a sound basis for project initiation

Reference:
http://www.prince2how2.com/2014/12/prince2-project-brief-template.html

Question 194

Which role is responsible for the quality of the specialist products delivered in the project?
Executive
Senior user
Senior supplier
Project assurance




Answer is Senior supplier

Reference Prince2 guide, section C.2.1:
" hold the senior supplier to account for the quality and integrity of the specialist approach and specialist products created for the project"

Question 195

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?
A description of the risk management procedure
An explanation of the company's risk appetite
The names of the assigned actionees for each risk
Estimations of the likelihood and impact of risks




Answer is A description of the risk management procedure

Reference: https://www.prince2primer.com/prince2-2017-risk-theme-changes/

Question 196

Identify the missing word in the following sentence:

The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
activities
processes
products
quality




Answer is processes

Reference:
http://www.innolead.co.bw/index.php/inno-content/cid/27/prince2/

Question 197

Which is a minimum requirement for applying the change theme?
To establish a change budget to fund changes in scope
To appoint the project manager as part of the change authority
To define the project's approach to baselining products
To record every issue that is raised in the issue register




Answer is To record every issue that is raised in the issue register

You must define a risk management approach covering the risk management procedure to be used, and the roles and responsibilities for risk management. You must maintain some form of risk register to record and manage risks and must ensure that risks are identified, assessed, managed and reviewed throughout the project. You must use lessons to inform risk identification and management.

Reference:
https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-6

Question 198

Why is the 'learn from experience' principle applied to a project?
To enable the project team to repeat successes from previous projects
To enable the project team to develop a business case for the project
To allow the project to be divided into management stages
To enable the project team to use tolerances to delegate authority




Answer is To enable the project team to repeat successes from previous projects

Reference:
https://link.springer.com/chapter/10.1007/978-3-319-23000-9_4

Question 199

What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance
1 and 2
2 and 3
3 and 4
1 and 4




Answer is 1 and 4

This process is a "handshake" between PM and TM. It consists of three stages: you agree with a work package, you execute it, you deliver it. There is nothing about project board.

Managing Product Delivery Activities

Accepting a Work Package: The Team Manager accepts the Work Package from the Project Manager and creates the Team Plan to manage the development of the products.
Executing a Work Package: The team produces the products, requests the quality checks, obtains approval, and reports to the Project Manager using the Checkpoint Report.
Delivering a Work Package: Delivering a Work Package is delivering proof that the products are complete.
This involves ensuring that the Quality Register is updated, that approvals are done, that products are delivered as described in the Change Control Approach , and that the Project Manager is notified.

Reference:
https://prince2.wiki/processes/managing-product-delivery/

Question 200

According to the 'tailor to suit the project' principle, what is the basis for effective project management?
That the appropriate number and type of meetings are held
That the project is divided into an appropriate number of stages
That the appropriate information is provided to make decisions
That the project method relates to the project's environment




Answer is That the project method relates to the project's environment

Reference:
http://prince2.wiki/Tailor_to_suit_the_project_environment

< Previous PageNext Page >

Quick access to all questions in this exam

Warning: file_get_contents(http://www.geoplugin.net/php.gp?ip=216.73.216.191): failed to open stream: HTTP request failed! HTTP/1.1 403 Forbidden in /home/passnexa/public_html/view/question.php on line 243