1. Activities to ensure the products are fit for purpose
2. Identified threats and opportunities
3. Problems and concerns to be managed informally
4. Roles responsible for reviewing the project's products
1 and 2
2 and 3
3 and 4
1 and 4
Answer is 1 and 4
Question 265
Which is a minimum requirement for applying the organization theme?
The project's approach to engaging with its stakeholders must be defined
Roles must be combined to reduce the number of individuals needed on the project
During a procurement the senior supplier must be appointed from the customer organization
The project team must change at each end stage of the project life cycle
Answer is The project's approach to engaging with its stakeholders must be defined
Question 266
What is the minimum number of management stages required by PRINCE2?
Two stages: to initiate and to deliver the project
One stage: to cover the whole project
Three stages: to initiate, to deliver and to close the project
Four stages: to start, to initiate, to deliver and to close the project
Answer is Two stages: to initiate and to deliver the project
Question 267
Which statement about applying the 'tailor to suit the project' principle is CORRECT?
PRINCE2 can be tailored to be used with any type of project
A technically complex project should NOT tailor PRINCE2
The tailoring of PRINCE2 is MOST appropriate for agile projects
A project which is part of a programme should NOT tailor PRINCE2
Answer is PRINCE2 can be tailored to be used with any type of project