Which is a benefit of applying the tailor to suit the project principle?
Project management becomes less bureaucratic
The capability of leadership is strengthened
The project environment complexity is reduced
The number of outputs is reduced
Answer is The project environment complexity is reduced
Question 292
Identify the missing word in the following sentence relating to one of the principles;
A PRINCE2 project should have [?] defined for each project objective.
themes
principles
processes
tolerances
Answer is tolerances
Question 293
What does the communication management approach define?
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project
1 and 2
2 and 3
3 and 4
1 and 4
Answer is 2 and 3
Question 294
What is an advantage of dividing the project into stages?
Detailed plans can be prepared closer to the time events will take place
the project board can delegate management of the project to team managers
The project can be authorized by the project manager on a stage by stage basis
The project brief can be updated towards the end of each stage
Answer is Detailed plans can be prepared closer to the time events will take place
Question 295
Which is a benefit of using PRINCE2?
It promotes consistency of project work and the ability to reuse project assets.
It includes techniques for critical path analysis and earned value analysis
It enables a project manager to be accountable for the success of a project
It prevents any changes once the scope of a project has been agreed
Answer is It promotes consistency of project work and the ability to reuse project assets.
Question 296
How does the managing product delivery process achieve its purpose?
By agreeing requirements for how project work should be undertaken
By producing highlight reports to enable the project board to oversee the work
By requiring the project manager to produce and monitor team plans
By escalating issues and risks that cannot be resolved within stage tolerance
Answer is By agreeing requirements for how project work should be undertaken
Question 297
Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?
Each party may have their own business case for undertaking the project
Both parties must apply the same external governance to the project
The risk appetite should be collaboratively set before the project starts
Management systems need to be unified for successful project delivery
Answer is Each party may have their own business case for undertaking the project
Question 298
During the initiating a project process, who specifies the required level of management control?
Corporate, programme management or customer
Project board
Project manager
Project assurance
Answer is Project board
Question 299
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
Project brief
Project initiation documentation
Project mandate
Project product description
Answer is Project initiation documentation
Question 300
Identify the missing words in the following sentence;
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.