According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?
Project board, project manager and project assurance roles
Directing, managing and delivering levels
Business, user and supplier interests
Corporate, programme management or the customer parties
Answer is Business, user and supplier interests
PRINCE2 states that a project should have defined and agreed roles and responsibilities within an organization structure that engages the Business, User and Supplier Stakeholder interests.
Which product defines how the project board should approve the management products produced during the 'initiating a project' process?
Communication management approach
Quality management approach
Project plan
Initiation stage plan
Answer is Initiation stage plan
The project manager should have agreed (as part of the initiation stage plan) the means by which the project board will review and approve the management products.
Reference:
Prince2 guide, 16.3
Question 247
Which product describes the method the project will use to engage with corporate, programme management or the customer?
Quality management approach
Communication management approach
Change control approach
Benefits management approach
Answer is Communication management approach
Question 248
Which is one of the six aspects of project performance to be managed?
To identify which role is responsible for producing the business case
To identify the project's outputs
To establish the controls to manage changes that may impact the project benefits
To establish a viable investment proposition
Answer is To establish a viable investment proposition
Question 250
Which role is responsible for appointing the senior user in a project that is independent from a program?
The project manager
The executive
Corporate, program management or the customer
Project assurance
Answer is The executive
PRINCE2 MAnual. Ref.C.2.1:
In addition to the project board’s collective responsibilities, the executive will:
design and appoint the project management team. Senior user and senior suppliers both appointed by executive