Question 311

According to the 'tailor to suit the project' principle, what is the basis for effective project management?
That the appropriate number and type of meetings are held
That the project is divided into an appropriate number of stages
That the appropriate information is provided to make decisions
That the right people are involved in appropriate roles




Answer is That the appropriate information is provided to make decisions

When tailoring PRINCE2, it is important to remember that effective project management requires information (not necessarily documents) and decisions (not necessarily meetings).

Reference:
Prince2 guide - 3.7

Question 312

Which is a minimum requirement for applying the quality theme?
Completed products must be reviewed using the PRINCE2 quality review technique
Independent reviews of the project must be carried out throughout its lifecycle
Approval records must be kept to show formal approval has been given
Quality criteria for products must be specified in their product descriptions




Answer is Quality criteria for products must be specified in their product descriptions

Reference:
PRINCE2 manual section 8.2

Question 313

Identify the missing words in the following sentence;

The first step of [?] is writing the project product description.
PRINCE2's recommended approach to defining and analyzing the products
The 'initiating a project' process
Producing the project mandate
PRINCE2's recommended issue and change control procedure




Answer is PRINCE2's recommended approach to defining and analyzing the products

Reference:
https://www.projex.com/creating-prince2-project-product-description/

Question 314

Which type of issue should be raised if a quality review finds that a product does not meet the criteria in the product description?
A request for change
An off-specification
A problem
A concern




Answer is An off-specification

Off-Specification; is something that should be provided by the project, but currently is not (or is forecast not to be). It might be a missing product or a product not meeting its specifications. It is one type of issue.

request for change; A proposal for a change to a baseline. It is a type of issue.

problem; A type of issue (other than a request for change or off-specification) that the project manager needs to resolve or escalate. Also known as a concern.

Question 315

Which process plans the activities of the closing a project process?
Closing a project
Managing a stage boundary
Directing a project
Starting up a project



Question 316

Which is a purpose of the progress theme?
To ensure that the change control approach is appropriate for the size of the project
To ensure that themes can be applied using techniques that are appropriate to the project
To ensure that responsibilities are defined for directing, managing and delivering the project
To ensure that the project remains viable against its approved business case




Answer is To ensure that the project remains viable against its approved business case

Reference:
https://www.simplilearn.com/prince2-progress-theme-tutorial-video

Question 317

Which are PRINCE2 principles?

1. Continued business justification
2. Managing product delivery
3. Controlling a stage
4. Learn from experience
1 and 2
2 and 3
3 and 4
1 and 4



Question 318

Which are purposes of a highlight report?

1. To escalate a tolerance deviation to the project board
2. To provide a summary of stage status to the project board
3. To allow the project board to monitor project progress
4. To update the project manager on the progress of a work package
1 and 2
2 and 3
3 and 4
1 and 4


Question 319

Which is a PRINCE2 time-driven control?
End stage report
Project brief
Project initiation documentation
Checkpoint report




Answer is Checkpoint report

Reference:
https://prince2.wiki/theme/progress/

Question 320

During the managing a stage boundary process, if external factors are identified that may affect the business justification for a project, which product should be updated?
Business case
Project brief
End project report
Highlight report



< Previous PageNext Page >