Prince 2 - Foundation

54%

Question 181

How does the project plan help to support the 'manage by stages' principle?
By identifying the customer's quality expectations
By defining products to ensure they are fit for purpose
By identifying the major control points and milestones
By estimating the timescales and costs of the project




Answer is By identifying the major control points and milestones


Question 182

Which is a factor when deciding the duration of a management stage?
The work packages to be delivered
The level of risk in the project
The cost of the stage
The number of products to be produced in the project




Answer is The level of risk in the project

The number of management stages within a project is clearly a balance between risk and cost as well as other factors. For example a high risk project would tend to have shorter management stages since the project board would want to review progress and the overall project status more often.

Reference:
https://www.prince2primer.com/the-design-of-prince2-management-stages/

Question 183

What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?
The senior user's responsibilities for realizing benefits
Statements of actual versus forecast benefits at reviews
The management actions needed to ensure benefits are realized
No specific documents related to benefits are necessary




Answer is The management actions needed to ensure benefits are realized

Prince 2 Manual Section 6.2
Benefits Management approach: Defines the management actions that will be put in place to ensure that the project's outcomes are achieved and confirm that the project's benefits are realized.

Your project must create and maintain a business justification (in the form of a business case), and you should review and update it throughout your project. You must define management actions to ensure the expected outcomes are achieved and the benefits are realized. You must define and document the roles and responsibilities for the business case and the management of benefits. Finally, you must produce and maintain a benefits management approach.

Reference:
https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes

Question 184

According to PRINCE2, why might there be more than one business case for a project?
There may be more than one management stage in the project
The project may be in a commercial environment with a number of suppliers
There may be more than one work package being delivered in the project
The project may be in a programme environment




Answer is The project may be in a commercial environment with a number of suppliers

The business case for a customer's project is separate from a supplier's business case for bidding for and working on that customer's project. The customer needs to ensure that its project is viable and risks are acceptable, bearing in mind the suppliers chosen. A supplier would have to ensure that it will benefit from the work it undertakes on the project. In other words, the project will be profitable from the supplier's perspective.

Reference:
https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/

Question 185

What is a benefits management approach used to assess?
How the project's products have performed when in operational use
The effectiveness of the project strategies
How the project has progressed against its plans
The suitability of the project management team structure




Answer is How the project's products have performed when in operational use

Reference:
https://mplaza.pm/prince2-benefits-management-approach-template/

Question 186

Why is the 'initiating a project' process used?
To decide which project approach is suitable for the project
To fully understand how the project objectives will be achieved before committing significant resources
To produce the required work packages
To enable corporate or programme management to give authorization to deliver a project




Answer is To fully understand how the project objectives will be achieved before committing significant resources

Reference:
https://www.whatisprince2.net/prince2-process-initiating-a-project.php

Question 187

Which is a purpose of the 'managing a stage boundary' process?
To enable the project board to approve the continuation of the project
To exercise overall control over the project while delegating day-to-day management
To assign work to be controlled by the team manager
To define the work that needs to be done to deliver the project product




Answer is To enable the project board to approve the continuation of the project

Reference:
http://prince2.wiki/Managing_a_Stage_Boundary#Objective

Question 188

Which product identifies how often stakeholders require information?
Communication management approach
Quality management approach
Change control approach
Risk management approach



Question 189

Which are purposes of the quality theme?
1. To implement continuous improvement during the project
2. To establish how the project will ensure that products created will be acceptable to key stakeholders
3. To ensure that the project is desirable and achievable
4. To identify, assess and control uncertainty
1 and 2
2 and 3
3 and 4
1 and 4




Answer is 1 and 2

Project is desirable and achievable is part of Business Case Theme not Quality.

Reference:
https://www.whatisprince2.net/prince2-theme-quality.php

Question 190

What is performed as part of the recommended risk management procedure?
A budget to investigate issues is allocated
Risk management practices are reviewed to ensure that they are performed effectively
Information about risks to the projects is sent to project stakeholders
Conflicts between the project and the programme board are resolved




Answer is Information about risks to the projects is sent to project stakeholders

As stated in section10.3.2 : 'Communicate', the fith step, operates in parallel as the outputs of any of the other steps may need to be communicted to stakesholders at any point in the process'

< Previous PageNext Page >

Quick access to all questions in this exam

Warning: file_get_contents(http://www.geoplugin.net/php.gp?ip=216.73.216.191): failed to open stream: HTTP request failed! HTTP/1.1 403 Forbidden in /home/passnexa/public_html/view/question.php on line 243