Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required
Which are advantages of a clear end to a project?
1. No further costs will be incurred by the project
2. Project products will be transferred to operations and support
3. All benefits will have been achieved
4. The project brief will be re-baselined
1 and 2
2 and 3
3 and 4
1 and 4
Answer is 1 and 2
Reference:
http://prince2.wiki/Closing_a_Project
Question 224
Identify the missing words in the following sentence;
The 'managing a stage boundary' process should be executed [ ? ] a management stage.
when a stage plan has been prepared for
at the beginning of
when all the delivery steps have been completed within